Why more and more candidates are eager to be a Project Management Professional (PMP) certified? PMP certification is the world’s leading project management certification, which supercharges careers for project leaders across industries and helps organizations find the people they need to work smarter and perform better. PMI PMP practice questions are available online to be your good study materials for helping candidates pass Project Management Institute (PMI) PMP exam smoothly. For checking PMP practice questions online, you can read PMP free dumps questions below and test yourself again and again.

Project Management Professional (PMP) Free Exam Dumps Below For Testing

Page 1 of 10

1. A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?

2. A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus.

What should the project manager do?

3. During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule.

What should the project manager do first?

4. The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.

What does that project manager need to do to make the team work in a collaborative way?

5. During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible

What approach should be used in this situation?

6. During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.

What should the project manager do first?

7. A vendor informed the project manager that a critical resource will be on a long leave of

absence. The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget

What should the project manager do next?

8. A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.

What should the project manager do first?

9. DRAG DROP

Drag the organizational characteristics on the left to the correct scenario on the right



10. A project manager is working on the implementation of new phases in the production process of a regulated industry.

Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)


 